FREE JHA TEMPLATE
Crane lift and rigging job hazard analysis (JHA) template
Crane lifts expose crews to struck-by loads, crane tip-over, power line contact and failed rigging. OSHA requires that equipment not be operated beyond its rated capacity (29 CFR 1926.1417(o)(1)) and limits who may be in the fall zone under a suspended load. Know the weight, inspect the gear and plan the route before the hook moves.
JHA template
Crane lift and rigging
| Step | Hazard | Controls |
|---|---|---|
| 1. Plan the lift and verify the load weight | Overload or a lift outside the crane chart | Choose a lighter pick, a split load or a closer… |
| 2. Inspect the crane and rigging | Worn rope, damaged hook or defective sling | Have a competent person begin a visual inspection… |
| 3. Set up the crane and check power lines | Crane contacts a power line | Have the utility owner de-energize and visibly… |
The task
Planning and making a crane lift of a steel member, precast piece or equipment, including rigging, signals, power line checks and landing the load.
Steps, hazards and controls
Controls run from most effective to least. A citation beside a control means an OSHA paragraph requires it; with no citation it is good practice.
| Step | Hazard | Controls |
|---|---|---|
| 1. Plan the lift and verify the load weight | Overload or a lift outside the crane chart |
|
| 2. Inspect the crane and rigging | Worn rope, damaged hook or defective sling |
|
| 3. Set up the crane and check power lines | Crane contacts a power line |
|
| Crane tips over from poor ground or wind |
| |
| 4. Rig the load | Load slips from the sling or spins during the lift |
|
| 5. Control the work area and the signals | Struck by the swinging superstructure or the suspended load |
|
| 6. Make the lift | Operator loses control of the load |
|
| 7. Land, unhook and secure | Crew caught between the load and the support |
|
| 8. Stow and tag | Crane or rigging left in an unsafe state |
|
Required PPE
- Hard hat
- High-visibility vest
- Cut-resistant gloves for rigging
- Safety glasses
- Safety-toe boots
What the standard says
Do not operate the equipment beyond its rated capacity. (29 CFR 1926.1417(o)(1))
“Compliance with rated capacity. (1) The equipment must not be operated in excess of its rated capacity.”
A competent person begins a visual inspection before each shift. (29 CFR 1926.1412(d)(1))
“A competent person must begin a visual inspection prior to each shift the equipment will be used”
Inspect rigging equipment before each shift. (29 CFR 1926.251(a)(1))
“General. (1) Rigging equipment for material handling shall be inspected prior to use on each shift and as necessary during its use to ensure that it is safe. Defective rigging equipment shall be removed from service.”
Employees must stay out of the fall zone while the operator is not moving a suspended load, except as the paragraph allows. (29 CFR 1926.1425(b))
“While the operator is not moving a suspended load, no employee must be within the fall zone”
Hold a power line planning meeting. (29 CFR 1926.1408(b)(1))
“Conduct a planning meeting with the operator and the other workers who will be in the area of the equipment or load to review the location of the power line(s), and the steps that will be implemented to prevent encroachment/electrocution.”
The operator must obey a stop signal from anyone. (29 CFR 1926.1417(y))
“The operator must obey a stop (or emergency stop) signal, irrespective of who gives it.”
A signal person must be provided in the situations the standard lists. (29 CFR 1926.1419(a))
“A signal person must be provided in each of the following situations:”
- 1926.1417 Operation
- 1926.1412 Inspections
- 1926.251 Rigging equipment for material handling
- 1926.1408 Power line safety (up to 350 kV): equipment operations
- 1926.1425 Keeping clear of the load
- 1926.1424 Work area control
- 1926.1419 Signals: general requirements
- 1926.1427 Operator training, certification, and evaluation
- 1926.1428 Signal person qualifications
Training
The employer must ensure each operator is trained, certified or licensed, and evaluated before operating covered equipment (29 CFR 1926.1427(a)). Signal persons must meet the qualification requirements (29 CFR 1926.1428(a)). Employees assigned to work near the equipment must be trained to recognize swing radius hazard areas (29 CFR 1926.1424(a)(2)(i)).
Frequently asked questions
- Does OSHA require a JHA for a crane lift?
- OSHA does not require a written JHA for a crane lift. The crane standard does require power line planning, inspections, operator qualification and work area control (29 CFR 1926.1408, 29 CFR 1926.1412, 29 CFR 1926.1427, 29 CFR 1926.1424). A JHA works well alongside a written lift plan.
- What goes in a crane lift JHA?
- Include lift planning, equipment and rigging inspection, set-up and power line checks, rigging, work area control, the lift and landing. List the load weight, radius and signal person by name.
- When is a signal person required?
- A signal person must be provided in each of the situations that 29 CFR 1926.1419(a) lists. The signal person must meet the qualification requirements of 29 CFR 1926.1428.
Related toolbox talks
- Crane safety: the free talk and the training kit
- Rigging safety: the free talk and the training kit
- Overhead crane safety: the free talk and the training kit
- Line of fire: the free talk and the training kit
- Falling and dropped objects: the free talk and the training kit
PRINT AND EDIT
JHA template pack, $29
All 20 task templates as editable Word and Excel files and as PDF, in English and Spanish, plus a blank master form. Change them for your site and your equipment and use them inside your company.
- 20 task JHA templates, editable Word (DOCX)
- The same 20 as Excel (XLSX) and PDF
- English and Spanish versions
- A blank master JHA form
- Hazards, ranked controls, PPE and the OSHA paragraphs for each task
Instant download. 30-day refund, no questions.